Passleader Provides Free 1Z0-567 PDF and VCE Dumps Ensure 100% Pass

Vendor: Oracle
Exam Code: 1Z0-567
Exam Name: Primavera P6 Enterprise Project Portfolio Management 8 Essentials

QUESTION 1
Calculated project user-defined fields __________and__________.

A.    are created by system administrators
B.    are managed by Configuration Management
C.    are associated with formulas
D.    are viewable in either the web interface or client
E.    are defined in the web interface and only viewable in the web interface

Answer: CE

QUESTION 2
Select the true statement regarding currencies.

A.    Only one base currency is supported per database.
B.    Currencies are updated daily per exchange rates.
C.    Only 10 currencies are supported in Primavera.
D.    Only two currencies are supported in Primavera.

Answer: A

QUESTION 3
Identify three best practice uses of Notebook topics.

A.    To document processes
B.    To explain a constraint
C.    To send out an email alert
D.    To explain baseline update
E.    To change user access
F.    To update actual costs
G.    To provide status information

Answer: ABG

QUESTION 4
You are an application administrator that has been asked to create a portfolio for an executive. You create the portfolio and have the user test to see whether it meets requirements. However there are a couple of projects that are missing. You look for the portfolio, but it is no longer visible to you. What is the cause of this problem?

A.    The global filters for the portfolio must be refreshed.
B.    You do not have read/write access to the portfolio.
C.    You created it for one user, and you are not that user.
D.    The projects were deleted in error.

Answer: C

QUESTION 5
You received an e-mail from a portfolio manager asking you to check performance metrics for the past months on each of the projects filtered for that portfolio. You cannot locate the portfolio that the email references. What is the probable cause?

A.    It is a user portfolio created by the portfolio manager.
B.    It is a user-filtered portfolio that has not been refreshed.
C.    You do not have the appropriate license for the web interface.
D.    You have not been assigned as a resource to the projects.

Answer: B

QUESTION 6
Identify the best definition of the EPS.

A.    The hierarchical definition of project budgets and actual costs.
B.    The hierarchical definition of reporting structures.
C.    The hierarchical structure of the security for projects.
D.    The hierarchical structure of the database of projects.

Answer: D

QUESTION 7
Identify the true statement regarding user-interface views.

A.    Deleting a user-interface view that has assigned users could cause user issues.
B.    Each user may be assigned to multiple user-interface views.
C.    User-interface views overwrite project and global security profiles.
D.    User-interface views are created and managed by individual users.

Answer: B

QUESTION 8
You are an implementation consultant working at a company where project schedules have been managed primarily with Microsoft Project, on individual desktops. The “projects” theoretically have been multiple-year projects. Your scope of work includes migrating project data from legacy project plans and setting up project planning standards. As you look into the current Microsoft Project plans, it becomes clear that the projects are not really multi-year projects. The plans have been managed by creating “new” projects within the old projects by skipping a few lines in what has become more of a program history. What approach would you recommend to retain the legacy data (which is a mandated requirement in the new Primavera system), while moving forward with a “one project, one plan” process?

A.    Import all MS Project plans directly into the P6 production database “as is.”
B.    Import MS Project plans but break out current in-flight work into separate projects.
C.    Create new projects only for in flight work identified in MS Project plans.
D.    Retire legacy project plans and start with new project planning standards.

Answer: B

QUESTION 9
You are an implementation consultant responding to the requirement that a cost account structure be set up in Primavera to be able to receive actual costs incurred by each contributing organization. There is also a cost account structure set up in the customer’s financial management system (FMS). What would be the easiest long-term recommendation for setup and maintenance of the cost account structure?

A.    Set up a cost account structure in Primavera that mirrors the FMS, and manually manage changes.
B.    Set up a cost account structure in Primavera and a global project code to map to FMS for Integration.
C.    Do not set up the cost account structure, and receive costed actuals only from the FMS.
D.    Set up integration between Primavera and the FMS to maintain all ongoing costing data.

Answer: C

QUESTION 10
You are in a governance organization that has established a project management methodology with work product and document requirements that must be included in every project. You are doing an audit prior to a gate review for a specific project. You are fairly certain that the project manager and project are in compliance with these requirements, but you cannot see the required work products and documents in the project workspace. How can you solve this problem?

A.    Go to Activities and search tor the Work Products and Documents by using an Activity view.
B.    Go to a dashboard and look for the Work Products and Documents in a portlet.
C.    Create a global activity code for required Work Products and Documents to call out activities.
D.    Go to the Project section and click Work Products and Documents to view the portlet.

Answer: D